OVERVIEW:

Construction is complete on NW Judd Parkway, the final section of the Judd Parkway loop around Town. 

The total project budget, including design, ROW and construction costs is $24,800,000.  The project is paid for through a combination of financing including $8.65 million in LAPP Grant Funding with the remainder paid from bonds approved by tax payers in the 2015 Transportation Bond.


Project Status: 

  • Current Progress: 

    • Project Proposed
    • Project Funding Approved
    • Under Design
    • Under Construction
    • ➙ Complete

CONTACT INFORMATION:


Project Contractor

ST Wooten Corporation
12204 Cleveland Road, Garner, NC 27529

Project Engineering Firm

Kimley Horn
421 Fayetteville Street, Suite 600, Raleigh, NC 27601

Fuquay-Varina Engineering Department 

For more information contact TOFV Engineering:
919-552-1400

Site Plan

NW Judd Pkwy Cover Sheet