Construction of infrastructure is underway for Sara Grove Subdivision, located at 7005 Kennebec Road. This conventional development features nine single-family lots averaging 30,906 square feet on 7.34 acres.
Project Status: Under Construction
Current Progress:
Preliminary Plans in Review
Preliminary Plan Approval
Town Board Approval: 7/8/2019
Construction Drawing Review
Construction Drawing Approval
Staff Approval: 3/18/2020
➙ Construction of Infrastructure
Construction of Homes
Contact Information:
Developer
Crown Builders and Developers 105 W Williams St Apex, NC 27502
Engineering Firm
The Curry Engineering Group 205 S Fuquay Ave Fuquay-Varina, NC 27526
Preliminary Plans
Rezoning:
Residential Agriculture (RA-CZD)
Town Board Approval: 2/5/18
Conditions:
The Town Board approved the Residential Agricultural Conditional Zoning District (RA-CZD), with the following conditions regarding site-specific standards:
Single family dwelling units only – no duplexes or townhomes.