The Process:
(Time Frame for review maximum 21 days unless notified otherwise)

  1. Application and all required information (see checklist) must be submitted.
  2. Plan Review (21 days)
  3. Review comments to the applicant.
  4. Revised plans submitted.

Submittal Checklist:
Submit one (1) completed Application for Site Plan (original copy, no faxes)

Site Plan Review Fee:
< 5 acres $625.00
> 5 acres $1250.00

>Any review after the 2nd review will require an additional fee of $200 per review.

  • 4 (four) maps (no larger than 24" x 36" standard engineer copies) FOLDED to an approximate 8.5"x11" size)
  • 1 (one) map 11 x 17"
  • Original signatures by stated parties on all forms.

 

Download Site Plan Process Forms:


>> Site Plan Application
>> Site Plan Improvement Contractors Form